See daily progress on Historic Cleveland Street
September 7, 2026 • 600 Block
New structural connectors are being added along the roof framing at 623–627 Cleveland Street to improve the connection between the roof and building structure.
Read moreSeptember 6, 2026 • 600 Block
Crews backfill, level and compact the open floor areas at 623–627 Cleveland Street, creating a firm base for the new concrete slab.
Read moreSeptember 5, 2026 • 600 Block
New wood ledgers are being positioned and mechanically fastened along the existing concrete masonry unit walls, adding horizontal framing as reconstruction progresses at 623–627 Cleveland Street.
Read moreSeptember 4, 2026 • 600 Block
Foundation work advances at 623–627 Cleveland Street as crews install reinforcing steel within the new footing forms.
Read moreSeptember 3, 2026 • 600 Block
Below-grade sanitary piping and fixture stub-ups are being installed along excavated plumbing routes at 623–627 Cleveland Street for the building’s new bathrooms.
Read moreSeptember 2, 2026 • 600 Block
Temporary shoring connections are installed at 639 Cleveland Street, providing structural support as demolition and building modifications continue.
Read moreSeptember 1, 2026 • 600 Block
Crews measure, assemble and install wood foundation forms at 623–627 Cleveland Street, preparing the excavated areas for reinforcing steel and concrete placement.
Read moreAugust 31, 2026 • 600 Block
Newly rebuilt front columns and wall sections at 623–627 Cleveland Street are receiving grout after masonry and reinforcing steel installation.
Read moreAugust 30, 2026 • 600 Block
Foundation work begins at 623–627 Cleveland Street as crews excavate sections of the existing floor area to prepare for new structural foundations.
Read moreAugust 29, 2026 • 600 Block
A 170-foot crane lifts rebar cages into newly constructed front columns at 623–627 Cleveland Street, preparing the entrance structure and storefront for the next phase of construction.
Read moreAugust 28, 2026 • 600 Block
The steel framework for the new front columns is taking shape as crews assemble and tie 19-foot-tall rebar cages at 623–627 Cleveland Street.
Read moreAugust 27, 2026 • 600 Block
New structural steel is being fabricated to connect with portions of the existing building that will remain at 623–627 Cleveland Street.
Read moreAugust 26, 2026 • 600 Block
Structural grout is placed within the reconstructed rear masonry wall at 623–627 Cleveland Street, surrounding the previously installed steel reinforcement as wall reconstruction advances.
Read moreAugust 25, 2026 • 600 Block
Wall preparation continues at 623–627 Cleveland Street as crews install and brace temporary plywood panels along the existing masonry walls.
Read moreAugust 24, 2026 • 600 Block
Compact equipment and hand tools are being used to carefully return soil around newly installed underground piping at 629–633 Cleveland Street.
Read moreFollowing preparation of the wall channels, workers assemble vertical reinforcing cages and secure the bars with ties and structural anchoring adhesive at 623–627 Cleveland Street.
Read moreAugust 22, 2026 • 600 Block
Reinforcing steel is being sized and prepared at 623–627 Cleveland Street as crews continue assembling the materials needed for the wall work.
Read moreAugust 21, 2026 • 600 Block
Brick and concrete block are being separated and removed from sections of the existing front wall as preparation work continues at 623–627 Cleveland Street.
Read moreAugust 20, 2026 • 600 Block
Following trench excavation, crews are beginning installation of the underground plumbing system that will support the renovated building.
Read moreExcavation work begins behind 629–633 Cleveland Street as crews prepare trenches for new underground plumbing.