See daily progress on Historic Cleveland Street
November 28, 2026 • 600 Block
Block by block, the new east wall at 635 Cleveland Street is taking shape as masons check each section for proper alignment.
Read moreNovember 27, 2026 • 600 Block
Workers weld galvanized steel components at the 629–633 Cleveland Street entry, creating the structural framework for the new storefront assembly.
Read moreNovember 26, 2026 • 600 Block
Fresh concrete fills the prepared footing forms at 635 Cleveland Street as crews establish the foundation for new masonry construction.
Read moreNovember 25, 2026 • 600 Block
Workers suspend and position new HVAC ductwork beneath the roof framing at 629–633 Cleveland Street.
Read moreNovember 24, 2026 • 600 Block
Workers install overhead duct straps at 623–627 Cleveland Street to support and secure future ductwork.
Read moreNovember 23, 2026 • 600 Block
Formwork is taking shape along the east wall at 635 Cleveland Street, preparing the foundation area for reinforcing steel and concrete placement.
Read moreNovember 22, 2026 • 600 Block
A new structural connection is taking shape at 639 Cleveland Street as steel embed plates are installed along the top of the south wall.
Read moreNovember 21, 2026 • 600 Block
The underside of the new roof deck is taking sahape at 629–633 Cleveland Street as welded connections tie the decking to the existing steel framing.
Read moreNovember 20, 2026 • 600 Block
A new foundation element is taking shape at 639 Cleveland Street as crews pour the front wall footing following formwork and reinforcement.
Read moreNovember 19, 2026 • 600 Block
Another structural step at 635 Cleveland Street: concrete is being pumped into the new west wall around the reinforcing steel.
Read moreNovember 18, 2026 • 600 Block
Roof reconstruction continues at 629–633 Cleveland Street as crews connect the new metal deck to the building’s existing steel roof framing.
Read moreNovember 17, 2026 • 600 Block
Roofers heat-weld new roofing membrane around metal ventilation ducts on the roof of 623–627 Cleveland Street.
Read moreNovember 16, 2026 • 600 Block
Foundation construction advances at 639 Cleveland Street as the new front footings move toward concrete placement.
Read moreNovember 15, 2026 • 600 Block
Masons install steel embed plates and reinforcing steel within the west masonry wall at 635 Cleveland Street.
Read moreNovember 14, 2026 • 600 Block
Mechanical systems are taking shape inside 623–627 Cleveland Street as contractors begin installing the ductwork that will distribute conditioned air throughout the building.
Read moreNovember 13, 2026 • 600 Block
Masons are building the west wall at 635 Cleveland Street with concrete masonry units above the recently completed foundations.
Read moreNovember 12, 2026 • 600 Block
The worn gypsum decking at 629–633 Cleveland Street has been removed as crews install a new metal roof deck.
Read moreNovember 11, 2026 • 600 Block
Another detail of the new façade is taking shape at 629–633 Cleveland Street as workers weld steel angles to the structural-steel joists.
Read moreNovember 10, 2026 • 600 Block
Reinforcing steel is being cut, assembled and tied for the front wall footing at 639 Cleveland Street.
Read moreNovember 9, 2026 • 600 Block
Reinforcing steel and concrete infill are integrated within the newly constructed west wall at 639 Cleveland Street as structural work progresses.
Read more